Multiple choices 16/50
Answer (Choose 1 answer)
B A. Spiral model is not a model but a process model generator
B. You always have to perform all the steps mentioned in the spiral model diagram
Next
C. It is suitable for very large high risk projects
D. It minimizes waste by allowing teams to tailor the effort put into different processes based on the risk involved in each cycle.
Which of the following is NOT true for Spiral model?