the product of your project your planned schedule in 5 weeks. Therefore, you must take action so that your project can finish 5 weeks sooner.
Please write down 2 solutions for this request.
Answer should be in this form:
FOOVERFLOW.COM
Solution 1:
Solution type: Crashing
Solution Detail: reduce activity x duration from y to z weeks.
VERFLOW.COM
FUOVERFLOWICOM
Zoom
Consequence: xxx
Solution 2:
Solution type: fast tracking
Solution detail: run the activity x and activity y in parallel.
Consequence: xxx