Kizspy Question: 3
(Choose 2 answers)
Which of the following statements about reaching agreement on requirements is accurate? Select two.
A. Signing off on requirements is an infallible method to prevent any changes later in the project.
B. All participants in the requirements approval process must understand what signing off implies.
C. The purpose of signing off is to freeze requirements and prevent any future modifications.
D. Reaching agreement on requirements ensures that both customers and developers have a shared
understanding of project objectives.