(Choose 1 answer)
You are the test manager and you are about the start the system testing. The developer tean change in requirements they will be able to deliver the system to you for testing 5 working da date. You can not change the resources (work hours, test tools, etc.) What steps you will tak finish the testing in time.
A. Tell to the development team to deliver the system in time so that testing activity will be fi
B. Extend the testing plan, so that you can accommodate the slip going to occur
C. Rank the functionality as per risk and concentrate more on critical functionality testing
D. Add more resources so that the slippage should be avoided
5