Which of the following is an example of project risk?
A. A particular computation may be performed incorrectly in some circumstances.
B. Response-times may be inadequate for a high-performance transaction processing system.
C. A system architecture may not adequately support some non-functional requirement(s).
D. Users, business staff or subject matter experts may not be available due to conflicting business priorities.