(Choose 1 answer)
Which of the following are the examples of the metrics-based approach and which are the examples of the
expert-based approach?(i) Categorizing the project based on its size and complexity; and then examines the historical data to determine the average duration of projects with similar size and complexity combinations
(ii) Building mathematical models in a spreadsheet which looks at industry averages for number of tests run by
a tester per day
(iii) Burndown charts are utilized to capture the effort being spent which is then fed into the team's velocity to
determine the amount of work the team can do in the next iteration.(
iv) Team member estimate testing effort based on their own experience of the effort needed to deliver and test the feature
A. (iii) and (iv) are metric-based; (i) and (ii) are expert-based
B. (i), (iii) and (iv) are metric-based; (iv) is expert-based
C. (i), (ii), (iii) are metric-based; (iv) is expert-based
D. (i) and (ii) are metric-based; (iii) and (iv) are expert-based