(Choose 1 answer)
Which of the following is correct about risk-based testing.
A. Risk-based testing is the idea that we can organize our testing efforts in a way that reduces the residual level of product and project risks when the system is delivered.
B. Risk-based testing uses risk to prioritize and emphasize the appropriate tests during test execution.
C. Risk-based testing starts with assigning risk level through reviewing the collated list of risk items to determine the risk priority number
D. The level of risk is determined by probability and risk rating