Project scope differs from product scope in that:
A. Project scope is the work that needs to be accomplished to deliver a product, service, or result.
B. Project scope completion is measured against the features, functions, and product requirements.
C. Product scope completion is measured against the project management plan including all subsidiary plans.
D. Product scope is the work that needs to be accomplished to complete a project