The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the critical path?
A. 13
B. 9
C. 11
D. 14
Activity
Duration
Predecessor
2
Start
4
A, E
6
3
B, C
7
Start
F
2
End
D, F