(Choose 1 answer)
You and your team have identified a risk that is a threat to your ability to successfully meet project objectives.
The risk involves team members from your company performing work which requires training, certification,and many hours of experience. You have one newly certified team member and others who are still in training.Which do you think is your best response to this risk?
A. Acknowledge your lack of expertise and set aside some contingency reserve to cover the risk.
B. Change the scope of the project so that this type of work is excluded and introduce a new risk, that of an unhappy sponsor.
C. Let the team do the work and see what happen, do not prepare any other response.
D. You have budget to hire external resources and there is a vendor you can hire who specialized in this type of work, hire them.