Consider a scenario in which you learn that your project is running two weeks behind schedule. How would you know if it is acceptable to be two weeks late?
A. Ask your executive management team
B. If the schedule baseline shows you are two weeks late, then it is not acceptable
C. If the team tells you the work cannot be completes any earlier than it is acceptable
D. Your variance thresholds should be documented in your project management plan, look there for guidance.