Which of the following is the most correct statement regarding management and contingency reserves?
A. Both of them are included into the cost budget of the project.
B. Both of them are not included into the cost budget of the project.
C. Management reserve is included into the cost budget but contingency reserve is not.
D. Contingency reserve is included into the cost budget but management reserve is not.
ntfi

  • Like
Reactions: fru

Thông tin

Category
PMG201c
Thêm bởi
Miwa84
Ngày thêm
Lượt xem
5,292
Lượt bình luận
40
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG201c_-_FE_-_FA_2023_1189.webp
File size
108.5 KB
Dimensions
1542px x 870px

Share this media

Back
Bên trên Bottom