20
hine: ADMIN
Student:
Server: Eng_EOS_ 14032 Exam Code: PMG201
Duration: 60 minutes
Open Code:
Show Question
Q mark: 1
Total Marks: 50
Vol 8
Time Left:58:39
Font: Microsoft Sans Serif
Size: 10
Multiple Choices
Answer (Choose 1 answer)
A project manager's primary responsibility is to deliver the product of the project within project constraints.Actions taken and changes made to the benefit of one constraint could negatively affect another. Which of the following best describes the major constraints on a project?
A. Scope, number of resources, and cost
B. Scope, cost, and schedule
C. Scope, schedule, cost, quality, risk, resources, and customer satisfaction
D. Schedule, cost, and number of changes
ntfi