Multiple Choices
(Choose 1 answer)
The Project Scope Statement should include the following:
A. Project exclusions, project constraints, project plan.
B. Project deliverables, project constraints, project team members.
C. Project deliverables, project constraints, project assumptions.
D. Project exclusions, project charter, project assumptions.