All of the following are inputs to estimating activity durations except:
A. Enterprise Environmental Factors & Organizational Process Assets
B. Risk Register & Scope Statement
C. Project Documents Updates & Requirements Specifications
D. Resource Calendars & Resource Breakdown Structure