The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the critical path?
A. 11
B. 14
C. 13
D. 9
Activity
Duration
2
4
Predecessor
Start
A, E
6
3
B, C
7
Start
F
2
End
D, F

9