Answer (Choose 1 answer)
When you use the RACI or Responsible, Accountable, Consult, Inform version of the RAM, those accountable persons are:
B A. Making the final decision
B. Being kept updated about project progress.
C. Completing the work
D. Providing subject matter expertise
Exit 16