(Choose 1 answer)
Which of the following is the most correct statement regarding management and contingency reserves?
A. Both of them are included into the cost budget of the project.
B. Both of them are not included into the cost budget of the project.
C. Management reserve is included into the cost budget but contingency reserve is not.
D. Contingency reserve is included into the cost budget but management reserve is not.