You have a project to build a new fence. The fence will form a square.Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other.Today is the end of day 3.
Side 4
Day 1
Day 2
SF
S
Day 3
Day 4
Status End of Day 3
Complete, spent $1,000
Complete, spent $90050% done, spent $600
Using the following project status chart to calculate project current SV:
-PF 75% done, spent $600
A. SV = $250
Key:S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned Finish
S
-F
-PF
PS
S
-PF
PS
F
B. SV = $300
C. SV = $150
D. SV = $200
E. SV = $50
F. SV = $100
Activity
Side 1
Side 2
Side 3


Q: 35

Thông tin

Category
PMG201c
Thêm bởi
dinhphong97
Ngày thêm
Lượt xem
4,262
Lượt bình luận
30
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
PMG201c_-_FESP24_1814.webp
File size
233.6 KB
Dimensions
1920px x 930px

Share this media

Back
Bên trên Bottom