Multiple Choices
(Choose 1 answer)
Which statement is not correct?
A. Project scope is the work that needs to be accomplished to deliver a product, service, or result.
B. Product scope completion is measured against the product requirement.
C. Project scope completion is measured against the project management plan and specially the project scope statement, the work breakdown structure (WBS), and the WBS dictionary.
D. Product scope is the work that needs to be accomplished to complete a project