In Earned Value Management Technique, you can compute the Estimate At Completion (EAC) by applying which of following formula? (Notes: BAC: Budget At Completion)
A. EAC = BAC + CPI
B. EAC BAC/CPI
C. EAC = BAC - SPI
D. EAC BAC * CPI