Which one of these most correctly defines management reserve?
A. Per our lesson, management reserve and contingency are exactly the same.
B. Management reserve is not tied to specific work packages it is for the entire project.
C. Management reserve is tied to specific work packages.
D. Management reserve is tied to a specific milestone or event.