Multiple Choices
OF
side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3.
Side 2
Side 3
Side 4
Day 1
Day 2
SF
S
-F
Day 3
Day 4
Complete, spent $1,000
Status End of Day 3
Complete, spent $90050% done, spent $600
-PF 75% done, spent $600
Key:S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned Finish
-PF
PS
S
-PF
PS
Using the following project status chart to calculate project current PV:
A. PV = $3,000
B. PV = $3,100
C. PV = $2,500
D. PV = $3,250
E. PV = $2,650
PV = 2,200
Activity
Side 1