Multiple Choices
(Choose 1 answer)
As you plan your project, the sponsor informed you that all team members will be assigned to your project for at most 50% of their available time. This is an example of:
A. Poor planning.
B. Wishful thinking.
C. A project demand.
D. A constraint.