Multiple Choices
☐ C
(Choose 1 answer)
To calculate late finish (LF) of an activity which has only one successor, you will
A. Take the late start of its immediate successor.
B. Take the early start of its immediate successor.
C. Take the late finish of its immediate successor.
D. Take the early finish of its immediate successor.