PMG201c_-_SP_2025_-_C2FE_3821.webp
K

PMG201c_-_SP_2025_-_C2FE_3821.webp

Kizspy Question: 3
(Choose 1 answer)
A project manager's primary responsibility is to deliver the product of the project within project constraints.
Actions taken and changes made to the benefit of one constraint could negatively affect another. Which of the
following best describes the major constraints on a project?
A. Scope, number of resources, and cost
B. Scope, cost, and schedule
C. Scope, schedule, cost, quality, risk, resources, and customer satisfaction
D. Schedule, cost, and number of changes