To calculate late finish (LF) of an activity which has more than one successor, you will
A. Take the earliest late start of its immediate successors.
B. Take the earliest early start of its immediate successors.
C. Take the earliest late finish of its immediate successors.
D. Take the earliest early finish of its immediate successors.