Kizspy | Question: 24
(Choose 1 answer)
A team member tells you that her work is too creative to provide you with a fixed single estimate for the
activity. You both decide to use the average labor hours (from past, similar projects) to develop a prototype.
This is an example of which of the following?
A. Parametric estimating
B. Three-point estimating
C. Analogous estimating
D. One-point estimating