Kizspy Question: 46
(Choose 1 answer)
During a risk brainstorming session, a team member identifies a risk. This particular risk does not seem to
belong to any of the categories in you Risk Breakdown Structure (RBS). How should you respond?
A. Chastise him for making up risks which cannot exist because there is not a category for such risks.
B. Ignore him and move on to another risk identified by a different team member.
C. Thank him for his work, but inform him that the risk cannot be included because it does not fit any of the
categories defined in the RBS.
D. Record the list in the risk register, discuss potential responses and make a note to update the RBS.