Kizspy | Question: 7
(Choose 1 answer)
One of the stakeholders of the project contacts the project manager to discuss some additional scope they
would like to add to the project. The project manager asks for details in writing and then works through the
Control Scope process. What should the project manager do next when the evaluation of the requested scope
is complete?
A. Ask the stakeholder if any more changes are expected
B. Complete integrated change control
C. Make sure the impact of the change is understood by the stakeholder
D. Find out the root cause of why the scope was not identified during project planning