Kizspy | Question: 8
(Choose 1 answer)
As part of planning you have created a scope baseline, a budget baseline, and a schedule baseline. Should
those baselines ever be allowed to change?
A. No, a baseline is a baseline.
B. Yes, it the schedule slips it is OK to update the baseline.
C. Yes, if the project manager approves baseline changes.
D. Yes, if the baseline is completely unachievable and the project sponsor approves it.