To calculate early start (ES) of an activity which has only one predecessor, you will
A. Take the early finish of its immediate predecessor.
B. Take the early start of its immediate predecessor.
C. Take the late finish of its immediate predecessor.
D. Take the late start of its immediate predecessor.