Kizspy | Question: 36
(Choose 1 answer)
FLUSTERI LOW LOW
You and another project manager disagree over whether a team member should work on your team or on her
team. You decide that the team member can work for the other project manager and suppose that the other
project manager will support you in the future. The truth is you wanted this person working on your project.
The conflict resolution approach you have used is:
A. Compromising
B. Smoothing
C. Confronting
D. Forcing