You have finished planning and have begun executing the project when the client asks if you would add some
important features to the product of the project. How are the triple constraints affected?
A. Time and cost may both be affected
B. Scope and quality would be affected but not cost
C. Cost must remain constant because resources are limited
D. Adding features will require additional cost but not time