Once the logic of a network is laid out, the project manager will conduct a forward pass and a backward pass
through the network. This will provide information regarding
and will identify the_
A. Resource shortages, high risk activities
B. The total duration of the project, critical path
C. The slack for each activity, high risk activities
D. The high risk activities, non-critical path