If a difficult stakeholder has low interest and low power then as the project manager you:
A. Can try to move them to be high interest and high power so that they are happy and do not get in your way.
B. Can try to move them to be high interest and low power so they do not get in your way.
C. Can monitor them, but do not bore them with excessive communication.
D. Can ignore them, they are as you need them to be.