Kizspy | Question: 21
(Choose 1 answer)
Once the logic of a network is laid out, the project manager will conduct a forward pass and a backward pass through the network. This will provide information regarding and will identify the
A. Resource shortages, high risk activities
B. The total duration of the project, critical path
C. The slack for each activity, high risk activities
D. The high risk activities, non-critical path