Kizspy | Question: 48
(Choose 1 answer)
One way to classify your stakeholders is to use the Power/Interest Grid. If a stakeholder is low interest / low power, what should the Project Manager do?
A. Monitor
B. Keep satisfied
C. Manage closely
D. Keep informed