In a project context, risk is defined as:
A. The probability of an event having a positive or negative effect on at least one project objective.
B. The impact of not completing the project on time and within budget.
C. An uncertain event that, if it occurs, will have a positive or negative effect on at least one project objective.
D. An uncertain event that, if it occurs, will have a negative effect on at least one project objective.