Kizspy | Question: 12
(Choose 1 answer)
FJOVERFLOW.COM
During project executing, a team member comes to the project manager because he is not sure what work he
needs to accomplish on the project. Which of the following documents contains detailed descriptions of work
packages?
A. WBS dictionary
B. Activity list
C. Project scope statement
D. Scope management plan