Kizspy | Question: 13
(Choose 1 answer)
The network diagram can be used to:
A. Control the cost performance of the project
B. Show project schedule performance over time
C. Identify project resource requirements
D. Identify opportunities to compress the project schedule
E. Help to justify project quality metrics