You and another project manager disagree over whether a team member should work on your team or on her
team. You decide that the team member can work for the other project manager in the afternoon and the other
project manager says it is OK for the team member to work for you in the morning. The truth is you both
wanted this person fulltime. The conflict resolution approach you have both used is:
A. Compromising
B. Smoothing
C. Confronting
D. Forcing