Kizspy Question: 3
(Choose 1 answer)
You have finished planning and have begun executing the project when the client asks if you would shorten the
project duration so that the project can finish 2 weeks earlier than the original plan. How are the triple
constraints affected?
A. Scope and cost may both be affected
B. Neither scope nor cost will be affected in any situation
C. Cost will reduce as the project duration is shortened and scope is not changed
D. There is no relevant option except the project must be cut down on scope