(Choose 1 answer)
☐ A
During a project team meeting, a team member suggests an enhancement to the scope that is beyond the
scope of the project charter. The project manager points out that the team needs to concentrate on
completing all the work and only the work required. This is an example of:
A. Change management
B. Scope management
C. Quality analysis
D. Scope decomposition
Back