Given Tm is the most likely of the estimated duration of the activity, To is the optimistic value and Tp is the
pessimistic one. The PERT (Program Evaluation and Review Technique) analysis calculates the expected
activity duration (Te) using which of the weighted average of these three estimates?
A. Te (Tm+4*To + Tp)/6
Back
Next
FUQ.sh
sh the exam.
B. Te (To+4*Tp + Tm)/6
C. Te (Tp+4*Tm + To)/6
D. Te (Tm +To+ Tp)/3