You have a project to build a new fence. The fence will
form a square. Each side is to take one day to build, and
$1,000 has been budgeted per side. The sides are
planned to be completed one after the other. Today is
the end of day 3.
Using the following project status chart to calculate
project current BAC:
☐ E
A. BAC $2,500
B. BAC $3,100
☐ F
C. BAC $3,250
Back
Next
D. BAC $4,000
E. BAC $3,000
F. BAC $2,200
FUQ.sh
sh the exam.
Activity
Side 1
S-
Day 1
-F
Day 2
Day 3
Day 4
Status End of Day 3
Complete, spent $1,000
Side 2
Side 3
S-F
S
-PF
Complete, spent $900
Side 4
PS
S
-PF
50% done, spent $600
PS
-PF 75% done, spent $600
Key:
S = Actual Start, F = Actual Finish, PS Planned Start, and PF = Planned Finish