SWE201_-_RE_-_FA_2023_1253.webp
pure_pearl

SWE201_-_RE_-_FA_2023_1253.webp

7
(Choose 1 answer)
Which of the following align with this principle:"Working software is the primary measure of progress."
A. If a team has delivered 5 features out of 10 features (or stories), team has made progress than 0% done)
B. If a team has written the requirements and done the design for 5 out of 10 stories, then th some progress (they are more than 0% done)
C. On a 10 month project, the team has been working for 5 months. Thus, the project is 50%


  • Like
Reactions: Hoàng Hùng

Thông tin

Category
SWE201c
Thêm bởi
pure_pearl
Ngày thêm
Lượt xem
4,933
Lượt bình luận
56
Rating
0.00 star(s) 0 đánh giá

Image metadata

Filename
SWE201_-_RE_-_FA_2023_1253.webp
File size
56.3 KB
Dimensions
1542px x 690px

Share this media

Back
Bên trên Bottom