(Choose 1 answer)
Which of the following align with this principle:
"Working software is the primary measure of progress."
A. If a team has delivered 5 features out of 10 features (or stories), team has made progress (they are more than 0% done)
B. If a team has written the requirements and done the design for 5 out of 10 stories, then the team has made some progress (they are more than 0% done)
C. On a 10 month project, the team has been working for 5 months. Thus, the project is 50% complete.