Answer (Choose 1 answer)
Select situations listed below where you would NOT use the unified process framework
A. Medium-sized project with some risks involved.
B. Very small, simple project where the problem and solution are well known.
C. Situation where the organization wants to deliver part of the application early to capture the market ahead of competition
D. All requirements are not known early in the project