(Choose 1 answer)
Which of the following is NOT true for the Waterfall model, V-model and Sashimi model?
A. In these models, we assume that we know requirements really well
B. In these models, the cost of change depends on how late we find out about the change. If problem requiring a change is found during the implementation phase, it will be more expensive to fix than one found during the design phase.
C. These models will be a good model to be used by a startup implement a new idea that is new to marke
D. In these models, the team is expected know the solution really well.